December 2013

Dec 1, 2013: slab warming party with Jan, Aunt Janie, and Cintia.

Dec 1, 2013: slab warming party with Jan, Aunt Janie, and Cintia.

Dec 12, 2013: Andy, Jan, and Aunt Janie warming the slab.

Dec 1, 2013: Andy, Jan, and Aunt Janie warming the slab.

Dec 3, 2013: standing frames for garage (steel) and flat (timber)

Dec 3, 2013: standing frames for garage (steel) and flat (timber)

Dec 3, 2013: Standing house frames

Dec 3, 2013: Standing house frames

Dec 3, 2013: Standing house frames

Dec 3, 2013: Standing house frames

Dec 3, 2013: standing wall frames

Dec 3, 2013: standing wall frames

Dec 3, 2013: Frames completed for both house and garage. Looking E towards main house.

Dec 3, 2013: Frames completed for both house and garage. Looking E towards main house.

Dec 3, 2013: Garage frame completed

Dec 3, 2013: Garage frame completed

Dec 3, 2013: Frames completed for both house and garage.

Dec 3, 2013: Frames completed for both house and garage.

Dec 3, 2013: frames completed for both the house and the garage.

Dec 3, 2013: frames completed for both the house and the garage.

Dec 3, 2014: garage and house frames completed.

Dec 3, 2014: garage and house frames completed.

Dec 5, 2013: garage cladding and roofing going on.

Dec 5, 2013: garage cladding and roofing going on.

Dec 6, 2013: garage completed.

Dec 6, 2013: garage completed.

Dec 6, 2013: garage completed... our new workshop.

Dec 6, 2013: garage completed… our new workshop.

Dec 6, 2013: garage completed... our new storage shed.

Dec 6, 2013: garage completed… our new storage shed.

Dec 9, 2013: 8mm reflective insulation thermal break and air barrier installed on granny flat. Front looking SW.

Dec 9, 2013: 8mm reflective insulation thermal break and air barrier installed on granny flat. Front looking SW.

Dec 9, 2013: 8mm reflective insulation thermal break and air barrier installed on granny flat. Back looking NE.

Dec 9, 2013: 8mm reflective insulation thermal break and air barrier installed on granny flat. Back looking NE.

Dec 10, 2013: Cintia trying out the little excavator.

Dec 10, 2013: Cintia trying out the little excavator.

Dec 10, 2013: digging the sewer line across the driveway.

Dec 10, 2013: digging the sewer line across the driveway.

Dec 10, 2013: Digging across the driveway for the sewer line.

Dec 10, 2013: Digging across the driveway for the sewer line.

Dec 10, 2013: Digging across the driveway for the sewer line.

Dec 10, 2013: Digging across the driveway for the sewer line.

Dec 13, 2013: "Versiclad Corrolink" sandwich panels being delivered for the roof. Unfortunately the crane was only on the Hiab truck and didn't stay to help put them on.

Dec 13, 2013: ‘Versiclad Corrolink’ sandwich panels being delivered for the roof. The crane was on the Hiab delivery truck and didn’t stay to help put the panels on the roof.

Dec 16, 2013: installing the roof panels.

Dec 16, 2013: installing the roof panels.

Dec 17, 2013: installing the roof panels.

Dec 17, 2013: installing the roof panels.

Dec 17, 2013: roof panel ridge detail.

Dec 17, 2013: roof panel ridge detail.

Dec 17, 2013: roof panels complete. Three guys, one day, structure, ceiling, insulation and roofing complete. Nice.

Dec 17, 2013: roof panels complete. Three guys, one day, roof structure, ceiling, insulation and roofing complete. Nice!

Dec 3, 2013: Bug Man heading up the roof to install foam closure strips under the ridge flashing

Dec 3, 2013: Bug Man heading up the roof to install foam closure strips under the ridge flashing

Dec 24, 2014: Windows installed, exterior closed in - front looking SW

Dec 24, 2014: Windows installed, exterior closed in – front looking SW

Dec 24, 2014: Windows installed, exterior closed in - back looking NW

Dec 24, 2014: Windows installed, exterior closed in – back looking NW

Dec 24, 2013: Interior closed in with floor protected looking towards bedrooms (W)

Dec 24, 2013: Interior closed in with floor protected looking towards bedrooms (W)

Dec 24, 2014: Interior with floor protected looking towards the kitchen (E)

Dec 24, 2014: Interior with floor protected looking towards the kitchen (E)

Dec 31, 2013: windows in and beginning to install the exterior gal cladding. Happy New Year!

Dec 31, 2013: beginning to install the exterior gal cladding. Happy New Year!